ST JOHN OF GOD HOSPITAL
Private hospital undertakes the Greenhouse Challenge.
Just because a hospital increases its size and its services doesn't mean
its energy consumption has to increase also. Effective energy management
and some wise capital investment led St John of God Hospital Murdoch to
record a 12.03% reduction in energy use even after a number of expansion
projects.
In late 2002, St John of God Hospital (SJGH) Murdoch undertook a site
evaluation in line with the Greenhouse Challenge. The evaluation comprised
a walk-through assessment to determine areas where reductions of greenhouse
gas emissions could be achieved.
The assessment of the 30,000 square metre floor area, 320+ bed health
campus identified that reductions in greenhouse gas emissions could be
realised in the areas of waste recycling, HVAC and building services,
medical gases and through the use of renewable energy.
In the following year, SJGH Murdoch became an active participant in the
Greenhouse Challenge by committing to a program to reduce greenhouse emissions
and to provide the necessary financial and administrative support to achieve
reduction targets.
With input from management and staff, a more rigorous approach to recycling
was adopted resulting in a more defined recycling program. This included
an increased number of categories for recyclable items, additional recycling
bins and the installation of a larger cardboard compaction plant. The
implementation of a more efficient recycling system was accomplished in
a relatively short period of time and did not require a large capital
outlay. It also assisted in raising the awareness of recycling and greenhouse
emissions throughout the campus.
The HVAC and building services required a more staged approach to identify
the main areas for reducing greenhouse emissions. HVAC services are typically
the main consumers of energy within a building. They are also the service
that can often provide the greatest opportunity to improve plant operation,
lessen operating costs and reduce greenhouse emissions in relatively short
payback periods to offset any capital investment.
Initiatives
A review of the hospital's HVAC systems carried out by ACMV Design Consultants
identified that the main areas to reduce energy consumption and greenhouse
emissions, in order of highest return on capital investment, were:
-
|
Improving the performance, staging and control of the 4,400 kW
chiller plant |
-
|
Improving the load profile and performance of the steam, heating
and hot water boiler plant (approx 2,700 kW) |
-
|
Replacing the existing pneumatic controls with digital controls
to improve the operation and control of eight of the original operating
theatre air-handling units and associated plant that operates 24/7 |
-
|
Improving the performance and control of the air-handling plant
serving the Day Surgery area by improving the existing digital control
routines and tuning the six air-handling units and associated plant. |
-
|
Use of variable speed drives on chilled water and condenser water
pumps where possible without compromising the operation of the chiller |
-
|
Gradual replacement of the existing pneumatic controls with direct
digital controls and the provision of improved control routines to
various air-handling units and associated plant and equipment. |
Since 2003, SJGH Murdoch, in conjunction with ACMV Design Consultants, has
progressively implemented a program of remedial works as funds have become
available. Works on the chiller and boiler plant have been completed and
work on the Operating Theatre and Day Procedure Unit air-handling plant
is currently in progress.
THE RESULTS
The Cost
The new 25 m3 bailing plant was installed for approximately $36,000, to
replace a smaller bailing unit and sulo bins that (combined) cost approximately
$1,000 a month to hire and operate.
The smaller system could not cope with the total cardboard disposal and
added approximately 30% to general waste disposal costs. To hire the larger
compactor would have cost approximately $1,200 per month plus operating
costs. Given the volume of the cardboard the site generated and capital
amortisation, purchasing the larger compactor resulted in a payback of
between 2 - 3 years.
The Greenhouse Challenge remedial works to the air conditioning plant
cost approximately $112,000. Annual energy consumption for 2004/2005 was
in the order of $950,000 per annum. Although the Hospital has expanded,
a reduction in energy consumption of around 12% has been achieved. This
suggests that a payback on capital expenditure of 2 - 3 years across the
site would be realised.
The Benefits
The benefits have been an overall reduction in greenhouse emissions since
commencement of the Greenhouse Challenge program.
The hospital has grown with the addition of a 70 bed ward, new Central
Sterile Supply Department, expanded Emergency Department, two additional
operating theatres and the installation of an 1100 kW chiller.
These changes resulted in an increase in occupied floor area from approximately
30,000 m2 to 37,000 m2 and an increase in patient bed days of 12%. However,
the hospital recorded a reduction of 15 % in greenhouse gas emissions
and a 12% reduction in energy consumption between November 2004 and November
2005.
Lessons Learnt
The initiatives implemented to date have resulted in a best practice review
of the operation and performance of the Hospital's building services and
assets and this identified some design and operational shortfalls. These
have resulted from the evolution of the site's building construction program
over the past 12 years.
This has prompted the Hospital to be more proactive in the design, construction
and commissioning stages of current and future projects to ensure that
building services and engineering systems installed operate as efficiently
as possible. This will also ensure that the systems are sustainable over
the longer term and are able to meet the ever-changing functional requirements
of the Hospital ensuring that items such as sustainability, energy efficiency
and energy management are built into the design of the building's services.
"The Greenhouse Challenge has committed SJGH Murdoch management
and staff to reduce greenhouse emissions and has allowed the identification
and prioritisation of remedial works to ensure that the capital outcomes
match investments, and that effective reductions in greenhouse gas emissions
are realised.
We are very pleased with the positive outcome of the greenhouse reduction
program and added benefits have been the improved efficiency of plant
operations, enhanced comfort levels throughout the Hospital and a reduction
in operating energy costs. We envisage reviewing our electrical services
once the main opportunities have been addressed in HVAC services"
-Rod Blockley, Chief Hospital Engineer, 2005.
|